The table give below give the information about the activities, their predecessors and time duration required to complete the activities of the…

BIT Operations Research · 2079 · Solved Question with Answer

The table give below give the information about the activities, their predecessors and time duration required to complete the activities of the project.

Activity A B C D E F G H
Predecessor - - A B A,D B C,E,F G
Time in weeks 5 12 6 3 2 6 14 22

Draw the network diagram and identify the critical activities and critical path. Also find the minimum time duration required to complete the project.

Solution

Please login to view the answer.