The table give below give the information about the activities, their predecessors and time duration required to complete the activities of the…
BIT Operations Research · 2079 · Solved Question with Answer
The table give below give the information about the activities, their predecessors and time duration required to complete the activities of the project.
| Activity | A | B | C | D | E | F | G | H |
|---|---|---|---|---|---|---|---|---|
| Predecessor | - | - | A | B | A,D | B | C,E,F | G |
| Time in weeks | 5 | 12 | 6 | 3 | 2 | 6 | 14 | 22 |
Draw the network diagram and identify the critical activities and critical path. Also find the minimum time duration required to complete the project.