Logo

The following is a summary of the entries in a contract ledger as on \( 31^{\text{st}} \) Chaitra 2081. Material purchased Rs. 70,000 Material from…

BBS Cost and Management Accounting · 2082 · Solved Question with Answer

The following is a summary of the entries in a contract ledger as on \( 31^{\text{st}} \) Chaitra 2081.

Material purchased Rs. 70,000
Material from store Rs. 200,000
Direct labour Rs. 100,000
Site office expenses Rs. 30,000
Other expenses Rs. 10,000
Plant installed Rs. 200,000
Sub-contract cost Rs. 10,000

The additional information are as follows:
i. 5% of the value of work certified still remained to be certified.
ii. Material returned to store Rs. 8,000.

iii. Material costing Rs. 15,000 sold at a profit of Rs. 1,000. iv. Depreciation on plant @ 15 % p.a. v. Material at site Rs. 10,000 vi. Cash received from contractor Rs. 540,000 being 90% of work certified. vii. Contract price Rs. 900,000.

Required:

a. Contract account

b. Contractee's account

c. Work in progress account

d. Balance sheet

Solution

Please login to view the answer.