The following information regarding labour are:

Standard:

Types No. Rate per hour
Skilled 2 Rs.4
Semi-Skilled 3 Rs.3
Un-Skilled 5 Rs.2
10
Types No. Rate per hour
Skilled 2 Rs.5
Semi-Skilled 4 Rs.4
Un-Skilled 4 Rs.2
10

Standard hours needed to work and actual hours paid for a week is 40 hours. Actual output produced by the workers is 340 units and Standard output per gang hour is 8 units 

Required: Labour Variances