The following activities must be completed in order to complete the project. Draw network diagram to reflect the inter relationship between activities of the project.
| Activity | P | Q | R | S | T | U | V | W | X |
|---|---|---|---|---|---|---|---|---|---|
| Prececessor | - | - | P, Q | Q | P | R | T, U | S, U | V, W |