Following standard and actual data are given to you: Labour Standard - No. Standard - Rate per hour Actual - No. Actual - Rate per hour Skilled 2 Rs.…

BBS Cost and Management Accounting · 2081 · Solved Question with Answer

Following standard and actual data are given to you:

Labour Standard - No. Standard - Rate per hour Actual - No.
Actual - Rate per hour
Skilled 2 Rs. 10 1 Rs. 11
Semi-Skilled 3 Rs. 7 3 Rs. 8
Unskilled 4 Rs. 5 5 Rs. 4
Total 9 9

Standard output per gang hours is 0.25 units. 8,000 hours needed to work and paid. Actual output produced 2,200 units in 8,000 hours. 

Required: Labour Variances. 

Solution