A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:

Activities A B C D E F G H I
Preceding activities – – – A A B, D B, D C, F E
Optimistic time 2 6 6 2 11 8 3 9 4
Most likely time 4 6 12 5 14 10 6 15 10
Pessimistic time 6 6 24 8 23 12 9 27 16

(a) Show the PERT network diagram for the project.

(b) Identify the critical activities.

(c) What is the expected project completing time and its variance?

Solution